CMMI Blog Special Series: 1st Part: This blog series on the cmmiconsultantblog.com is a systematic and structured coverage of CMMI Process Areas starting from Maturity Level 2 to Maturity Level 3: using CMMI –DEV, Version 1.3, as the Reference CMMI Model: As CMMI Consultant, during CMMI Consulting assignment if you are asked about the steps, inputs and outputs of Project Planning (PP) Process Area, what would be your response:

CMMI FAQ 0


25th June, 2015

For the above-mentioned question, CMMI Consultants may take inputs from the following:

The Project Planning starts with the signing of contract, issuance of scope of work document and conduct of Project Initiation Meeting by the Program Manager/Account Manager. During the Initiation Meeting the resources are allocated and commitments from the different stake holders are taken.

Following documents are provided as the input to the Project Planning Phase:

  • Contract Document
  • Project Scope of Work Documents
  • Minutes / Presentation of Project Initiation Meetings
  • Project Estimation Sheet
  • Project Initiation Note (PIN)

During the Project Planning following activities are being conducted by the Project Manager along with the team:

  • Identify suitable Process Model.
  • Identify major Work Products / Milestones
  • Identify Critical Path
  • Identify Project Specific Defined Process / Tailoring
  • Select Reusable Components/Artefacts
  • Identify Assumptions / Constraints / Dependencies
  • Identification of Risks and Mitigation Plan
  • Identify Issues and Action Plan
  • Resources Planning / Scheduling
  • Develop Communication Plan
  • Identify Tools for Project Execution
  • Identify Configuration Management Activities
  • Identify Quality Management Activities:
  • Selection of measures for the project and its goals.
  • Planning for reviews and audit.
  • Planning for testing.
  • Develop criteria for revising Project Management Plan (PMP)
  • Review of Project Management Plan, Project Schedule
  • Review and Re-estimate of effort and Size.
  • Approval of Project Management Plan

Outputs created during the implementation of the Project Planning activities are as under:

  • Project Management Plan (PMP)
  • Project Schedule
  • Review records of Project Management Plan
  • Risk / Issue Tracking Sheet /Log or Risk/Issue Tracking Tool
  • Resource Sheet for Hardware, Software and Human Resources
  • Training Sheet for the Team Members
  • Reusable Component Log

The above is not an exhaustive coverage of the Project Monitoring and Control (PMC), CMMI Process Areas but is substantive enough to create a good foundation of the project monitoring and execution process in an organization.

Source: CMMI for Development Version 1.3

Share this:

  • Click to email a link to a friend (Opens in new window)
  • Click to print (Opens in new window)
  • Click to share on Facebook (Opens in new window)
  • Click to share on Twitter (Opens in new window)
  • Click to share on LinkedIn (Opens in new window)
  • Click to share on Tumblr (Opens in new window)
  • Click to share on Pinterest (Opens in new window)
  • Click to share on Reddit (Opens in new window)

Like this:

Like Loading...

Related


Published by CMMI Consultant


cmmi, cmmi consultant, cmmi consultants, cmmi consulting, cmmi for development, project planning



Previous Post

Is there a central web site, repository or data base of CMMI were I could search that lists all companies who have assessed as per SCAMPI “A” assessment methodology of CMMI?

Next Post

CMMI Blog Special Series: 2nd Part: This blog series on the cmmiconsultantblog.com is a systematic and structured coverage of CMMI Process Areas starting from Maturity Level 2 to Maturity Level 3: using CMMI –DEV, Version 1.3, as the Reference CMMI Model: As CMMI Consultant, during CMMI Consulting assignment if you are asked about the steps, inputs and outputs of Project Monitoring and Control (PMC) Process Area, what would be your response:

Leave a Reply Cancel reply


Sidebar


Author: Rajendra Khare


Rajendra's LinkedIn Profile
Rajendra is a qualified and certified Lead Appraiser and Instructor for the following :

  • SCAMPI High Maturity Lead Appraiser (Certified)
  • CMMI Institute-Certified SCAMPI v1.3 Lead Appraiser for Acquisition (Certified)
  • CMMI Institute-Certified SCAMPI v1.3 Lead Appraiser for Development (Certified)
  • CMMI Institute-Certified SCAMPI v1.3 Lead Appraiser for Services (Certified)
  • CMMI Institute-Certified Introduction to CMMI-DEV v1.3 Instructor (Certified)
  • CMMI Institute-Certified Services Supplement for CMMI-DEV Instructor (Certified)
  • CMMI Institute-Certified CMMI-DEV Level 2 for Practitioners Instructor (Certified)
  • CMMI Institute-Certified CMMI-DEV Level 3 for Practitioners Instructor (Certified)
  • CMMI Institute-Certified SCAMPI B & C Team Leader for Acquisition (Certified)
  • CMMI Institute-Certified SCAMPI B & C Team Leader for Development (Certified)
  • CMMI Institute-Certified SCAMPI B & C Team Leader for Services (Certified)

Rajendra is Lead Assessor for ISO 9001 (QMS), ISO 14001 (EMS), OHSAS 18001 (OHSMS) since 1994

International Automotive Task Force (IATF) approved Lead Assessor for Automotive Standard TS 16949:2009

Lead Assessor for ISO 27001 (ISMS) and ISO 20000-1 (ITSM)

Rajendra has 25 years experience in the industry.


Tags

cmmi cmmi-acq cmmi-dev cmmi-svc cmmi appraisal CMMI Assessment cmmi benefits CMMI Certification cmmi consultant cmmi consultants cmmi consulting cmmi faq CMMI for Acquisition cmmi for development cmmi for services cmmi high maturity cmmi implementation cmmi institute cmmi maintenance cmmi maturity level cmmi maturity level 2 cmmi maturity level 3 cmmi model cmmi process cmmi process improvement cmmi services configuration management dqs india high maturity Information Security iso 9001 maturity level metrics opd organizational training pal PPQA process improvement qms requirements management risk risk management sam sepg supplier agreement management